Relocation of a Press Line Between Two Halls

The Task

The customer reorganized its production operations and therefore needed to relocate an entire press line from one production hall to another. Production downtime had to be kept to an absolute minimum, with only 48 hours available for the complete relocation, including dismantling, transportation, reinstallation, and restart.

What We Did

We prepared the relocation with a detailed, hour-by-hour schedule. Before the shutdown, we surveyed both production halls, inspected the foundations and utility connections at the new location, and marked out the exact positions of the machines in advance. Once the shutdown began, we dismantled the line section by section, documenting and labeling every unit and connection. We then transported the presses and auxiliary equipment using heavy-duty machinery moving equipment. In the new hall, we positioned, leveled, and secured the machines, then reconnected the power and control systems. Finally, we conducted a test run to verify the operation of the entire line.

The Result

The press line was restarted after just 41 hours — 7 hours ahead of the 48-hour deadline. Production resumed as planned in the new hall. Upon handover, the customer received the complete relocation documentation and the handover report.