Positioning of a 42-Ton Machining Center
The Task
The customer had purchased a new 42-ton CNC machining center and needed it to be installed in the existing production hall. The machine had to be positioned next to operating production lines in a confined space, so the entire moving and positioning process had to be planned and executed with a high degree of precision.
What We Did
After conducting an on-site assessment, we prepared a lifting and moving plan. We checked the load-bearing capacity of the floor and the condition of the foundation. The machine was moved through the production hall using a specialized roller transport system and hydraulic lifting equipment. It was then positioned in its final location according to the manufacturer’s specifications, precisely leveled, and secured. Throughout the entire process, the neighboring machines continued operating without interruption.
The Result
The machining center was positioned on schedule and within the tolerances specified by the manufacturer, ready for commissioning. Upon handover, the customer received the complete moving and positioning documentation, along with the handover report.