Steel support structure for a new conveyor system in the Bridgestone production hall

Installation of 120 Tonnes of Steel Structure for a New Conveyor System at Bridgestone

We installed 120 tonnes of steel structure for a new conveyor system at Bridgestone Tatabánya Kft. The structural elements were installed on a just-in-time basis straight after fabrication, with surveyed setting-out and a schedule aligned with the production cycle.

Challenge: installing heavy steelwork inside a running plant

The support structure for the new conveyor system had to be built in a running plant, where the work must fit the production cycle. The 120 tonnes of steel called for accurate setting-out and tight scheduling.

The new structure had to connect to existing receiving structures, which needed on-site modification, and fully enclosed sections required lighting.

Solution: just-in-time installation with survey-grade accuracy

We followed an installation schedule coordinated with the production cycle. The main tasks were:

  • installing 120 tonnes of steel structure for the new conveyor system,
  • just-in-time installation directly after fabrication,
  • surveying work for setting out the columns,
  • aligning the installation schedule with the production cycle,
  • on-site modification of existing receiving structures,
  • installing the equipotential bonding (EPH) network for the new structure,
  • installing lighting in fully enclosed structural sections.

Surveyed setting-out ensured accurate column positions, and just-in-time installation kept the structural elements arriving on schedule.

Forklift and blue steel columns during conveyor steel structure installation

Result: a ready foundation for the new conveyor system

The 120-tonne steel structure was accurately set out, connected to the existing structures and fitted with equipotential bonding and lighting, ready for the installation of the new conveyor system.

Because the work followed the production cycle, the steelwork was built while the plant kept running, preparing the ground for the production line installation.