Mobile crane inside the production hall during the BB121 mixer replacement

BB121 Mixer Replacement in 4 Working Days Without Disrupting Production at Bridgestone

In a production plant of Bridgestone Tatabánya Kft., we replaced the BB121 mixer and its hopper. The mixer body was exchanged in 4 working days on a round-the-clock schedule without disrupting production, and we then supported commissioning and validation.

Challenge: replacing high-value equipment in a tight time window

In a running plant, only a short window is available to replace key equipment. For the BB121 mixer, 4 working days were available to exchange the mixer body without halting production.

Differences between the old and new mixer had to be resolved on site, the gearbox-to-mixer coupling required high-precision alignment, and the equipment had to be validated together with its fire suppression system.

Solution: 24/7 working and precision alignment

Because of the tight deadline, we worked continuously around the clock. The main steps were:

  • dismantling the old mixer body, then positioning and fine-adjusting the new one,
  • replacing the couplings between mixer and gearbox and aligning them with a laser shaft alignment tool,
  • geometry and position measurement, with precision levelling to 0.02 mm/m,
  • modifications to bridge the differences between the old and new mixer,
  • electrical and piping work,
  • commissioning and testing the fire suppression system,
  • validating the complete installation.

The work was carried out by our team of installation specialists, covering mechanical, electrical and piping tasks.

Result: a validated mixer with no disruption to production

The BB121 mixer and hopper replacement was completed in 4 working days without disrupting production. The new mixer body was handed over levelled to 0.02 mm/m, with laser-aligned couplings, a working fire suppression system and full validation.

The client was able to replace a high value asset without interrupting production.